PAINTING STEEL BOATS

 

Remove rust and scales from the surface through sandblasting. Remove dust using a dry cloth or an air jet (do not use any solvent otherwise adhesion of the following coat can be impaired). If necessary degrease the surface with our antisilicone solvent SOLVENTE 102 before sandblasting.

Apply one coat of PRIMEPOX. It is advisable to apply this product with a brush, as this would facilitate the absorption of the product into the pores and the amalgamation of eventual impurities with the film.

Where necessary apply one or more coats of our EPOXY FILLER, without sanding between the coats if they are applied within 16 hours from each other (at 20° C).

After this stage the painting cycle changes depending on the part of the boat we wish to paint.

 

HULL

  • Sand with coarse sandpaper (n.100-120)

  • Apply two or three coats of ROSTAR (coal-tar epoxy anticorrosive paint) with a total consumption of 0,5 litres per square meter. For a good adhesion it is necessary to apply the coats within 24 hours from each other (at 20° C), during summer this interval will be between 12 and 16 hours. Note that this product can be replaced with our epoxy solventless protective coating BARRIER. After applying BARRIER the surface must be sanded with medium sandpaper (n.150-180).

  • Apply one coat of FIBERGLASS PRIMER (consumption: 12 square meter per liter)

  • Apply two coats of our antifouling SUPER 505, or MARLIN TF, or MAXIMA (consumptoion: 8 square meter per liter per coat).

 

TOPSIDE

  • Sand the surface with medium sandpaper (n.120-150)

  • Apply one or two coats of our epoxy coating EPOPLASTIC AS (consumption: 8 square meters per liter per coat).

  • After at least 24 hours at 20° C sand the surface with sandpaper n.200-240

  • Apply two coats of our polyurethanic enamel EVERGLOSS (consumption: 8 square meters per liter per coat by brush, 20-30% more by spraygun). No sanding is necessary if the two coats are applied between 6 and 8 hours.

 

BILGES AND INDOOR PARTS

  • Apply two full coats of EPOGEL